The three levels of bathroom renovation

As with kitchens, bathroom quotes cluster into three bands, and the difference between them is how far back to the brick you go.

LevelWhat it coversTypical 2026 cost
Cosmetic updateRe-tile over sound substrate, new basin, toilet, taps and accessories. Layout and plumbing unchanged.R25,000 – R50,000
Full remodelStrip to brick, new waterproofing, new tiling floor and walls, new sanitaryware, new lighting and extraction.R60,000 – R120,000
Re-plan / high-endLayout moved, freestanding bath, frameless glass, underfloor heating, stone or large-format tiles.R130,000+

The gap between a cosmetic update and a full remodel is not mainly materials — it is that a full remodel replaces the waterproofing, and a cosmetic update leaves whatever is under the old tiles in place. That single difference is why the two bands are worth thinking about carefully rather than just picking the cheaper one.

Waterproofing: the line item that decides everything

Waterproofing costs roughly R3,000 to R8,000 on a standard bathroom — about 5 to 8 percent of a full remodel. It is invisible the moment the tiles go on, which is precisely why it is the first thing removed from a quote that needs to come down.

The cheap bathroom quote trapThe most common renovation complaint we see is a bathroom done R20,000 cheaper — with the waterproofing skipped. The leak appears a year later in the passage ceiling or the adjoining bedroom wall, and fixing it means stripping out brand-new tiles and starting again. The cheap quote becomes the most expensive one.

A quote that takes waterproofing seriously will name three things: the system (a cementitious slurry, a liquid-applied membrane, or a sheet membrane), the area it covers, and the curing time before tiling. As a minimum the coverage should be the full shower enclosure, the entire floor, and 150mm up the walls beyond the wet area. In a shower, the membrane should run to at least 1.8m up the walls.

Two details separate a proper job from a box-ticked one: the membrane must be dressed into the drain outlet rather than stopping short of it, and internal corners should be reinforced with tape or fillets. Corners and the drain are where failures actually start.

Where the money actually goes

For a full remodel in the R60,000–R120,000 band, the split runs roughly as follows.

ComponentShare of budgetTypical range
Labour across all trades40–50%R25,000 – R60,000
Tiles and tiling materials15–25%R9,000 – R30,000
Sanitaryware (toilet, basin, bath or shower)15–20%R9,000 – R25,000
Taps, mixers and fittings8–12%R5,000 – R15,000
Waterproofing5–8%R3,000 – R8,000
Strip-out, rubble removal, making good5–10%R4,000 – R12,000

Labour dominates because of sequencing. Demolition, plumbing first fix, waterproofing, tiling, plumbing second fix, electrical and painting each have to wait for the one before, and several involve curing time in between. You are paying for coordination as much as for hours.

Tiles are where budgets flex most easily. A perfectly good ceramic wall tile starts around R150/m²; large-format porcelain runs R400–R900/m². Large formats also cost more to lay, because they need a flatter substrate and more careful setting.

Bath-to-shower conversions

The most requested single change in South African bathrooms, and usually worth doing in a house where a second bath already exists.

ScenarioTypical cost
Straight swap — shower sits in the old bath footprint, drain stays putR20,000 – R30,000
Drain moved, floor built up to create fall, frameless screenR30,000 – R45,000
Full wet-room conversion with level-entry floorR45,000 – R80,000

The variable that moves the price is the fall to the drain. Water has to run downhill, and a bath's waste sits at a different height from a shower's. If the floor screed has to be built up or cut back to create the fall, the job grows. Ask the contractor to explain how the fall will be achieved before signing — it is the question that separates a R22,000 quote from a R40,000 one.

One practical note if you are considering resale: removing the only bath in a family home is a decision estate agents will comment on. A shower-only house narrows the buyer pool for families with small children.

The costs that catch people out

How long it takes, and why

A full bathroom remodel takes two to three weeks, and the schedule is dictated by curing rather than labour.

StageTypical duration
Strip-out and rubble removal1 – 2 days
Plumbing and electrical first fix2 – 3 days
Screed and waterproofing, including cure2 – 4 days
Tiling floor and walls3 – 5 days
Grouting and cure1 – 2 days
Sanitaryware, second fix, glass, paint, snags2 – 4 days

If a contractor offers to finish a full bathroom in five days, they are compressing the waterproofing and adhesive cures. That is the single most common cause of a bathroom that leaks within two years, and it is invisible on handover day.

What should be in a bathroom quote

Red flags

Frequently asked questions

How much does a bathroom renovation cost in South Africa?
A cosmetic update — re-tiling, new basin, toilet and taps on the same layout — costs R25,000–R50,000. A full strip-to-brick remodel costs R60,000–R120,000. A bath-to-walk-in-shower conversion on its own is typically R20,000–R45,000.
How much does it cost to convert a bath into a shower?
R20,000–R45,000. That covers removing the bath, re-routing the waste, creating the fall to the drain, waterproofing, tiling and fitting a screen and mixer. The price rises if the drain moves more than a metre or the floor needs building up.
How much does bathroom waterproofing cost?
R3,000–R8,000 for a standard bathroom — about 5–8% of a full remodel. It is the one line item that should never be cut. A failed shower waterproofing means stripping out brand-new tiles to fix it.
How long does a bathroom renovation take?
Two to three weeks for a full remodel. The schedule is set by curing, not labour — waterproofing must cure before tiling, and adhesive and grout must cure before the shower is used.
Can I renovate a bathroom without moving the plumbing?
Yes, and it is the biggest saving available. Keeping the toilet, basin and shower where they are avoids re-routing supply and waste pipes and the chasing and making good that follows. Moving a toilet is the most expensive single change, because the soil pipe needs a specific fall.
Do I need a plumbing certificate of compliance?
A plumbing COC is required when a property in the City of Cape Town is transferred, and new plumbing should be done to a standard that would pass inspection. If you are renovating with a sale in mind, having the plumber issue the certificate at the end of the job is far cheaper than remediating later. See our plumbing COC guide.
What is the most expensive part of a bathroom renovation?
Labour, at 40–50% of a full remodel. A bathroom is small but involves six trades in sequence, each waiting on the one before. That sequencing, not the materials, is what you are mostly paying for.