The three levels of kitchen renovation

Almost every kitchen quote falls into one of three bands, and knowing which one you are asking for is the single most useful thing you can do before speaking to a contractor. The bands are not about quality — a well-executed facelift beats a badly executed refit — they are about how much of the kitchen you are actually replacing.

LevelWhat it coversTypical 2026 cost
FaceliftNew doors and drawer fronts on sound carcasses, new countertop, new splashback, paint. Layout unchanged.R30,000 – R70,000
Mid-range refitAll-new cabinetry, new tops, new sink and taps, new appliances, new lighting. Layout largely unchanged.R80,000 – R180,000
High-end / re-planCustom joinery, stone tops, moved plumbing and electrics, walls altered, integrated appliances.R200,000+

The jump between the first two bands is mostly cabinetry. The jump to the third is mostly movement — the moment the sink, stove or fridge changes position, you are paying a plumber and an electrician to re-route services, and a tiler and plasterer to make good afterwards.

The single biggest saving availableKeeping the existing layout removes the two most expensive variables from a kitchen renovation. If your current layout works and only looks tired, a facelift delivers most of the visual change for roughly a third of the cost of a refit.

Where the money actually goes

For a typical mid-range refit in the R80,000–R180,000 band, the split looks roughly like this. The percentages matter more than the rands, because they tell you which decision will move your total.

ComponentShare of budgetTypical range
Cabinetry35–45%R30,000 – R90,000
Countertops15–25%R12,000 – R45,000
Appliances10–20%R10,000 – R60,000
Plumbing & electrical8–15%R8,000 – R25,000
Tiling & splashback5–10%R4,000 – R15,000
Strip-out, making good, paint5–10%R5,000 – R15,000

Two things follow from that table. First, if a quote is far cheaper than another, the difference is almost always in cabinetry or tops — ask what board and what stone, not why it is cheaper. Second, appliances are the easiest line to control: they are the one component you can buy separately, on sale, without affecting the build.

Cabinetry: the biggest single cost

Kitchen cabinetry is priced per linear metre of run — measure along the wall, ignore the corners. Most Western Cape kitchens are between 4 and 8 linear metres.

MaterialWhat it isPer linear metre, installed
MelamineChipboard core with a bonded melamine face. The standard budget option.R3,000 – R5,000
Supawood / MDF, sprayedDenser board with a sprayed paint finish. Takes detail; the mid-market default.R5,000 – R8,000
Solid timber / custom joineryMade to measure by a cabinetmaker, usually for non-standard spaces.R8,000 – R15,000

A word on the carcasses, because it is where corners get cut invisibly. The carcass is the box; the door is what you see. A cheap kitchen often pairs decent-looking doors with 16mm chipboard carcasses and stapled backs, which sag under a stone top within a few years. Ask for the carcass board thickness — 16mm is standard, 18mm is better — and whether the backs are grooved in or stapled on.

Hinges and runners are the other silent variable. Soft-close hinges and full-extension drawer runners from a known brand add perhaps R3,000–R6,000 to a kitchen and are the parts you touch every single day. It is a small percentage of the total and the first thing people regret saving on.

Countertops compared

Countertops are priced per square metre of surface, and the material choice can swing a kitchen budget by R30,000 on its own.

MaterialPer m², installedWorth knowing
LaminateR700 – R1,400Cheapest by far. Cannot take heat; chips at the edges; swells if water gets into a cut.
Solid surface (acrylic)R1,800 – R3,000Seamless joins, repairable if scratched. Less heat-tolerant than stone.
Engineered quartzR2,500 – R4,000The best all-round value. No sealing, very stain-resistant, consistent colour.
GraniteR2,200 – R4,500Natural stone, every slab different. Needs sealing periodically.
MarbleR3,500 – R7,000Beautiful and porous. Stains from wine, lemon and oil. Not a practical family kitchen top.
Templating matters more than the materialStone tops are cut from a template taken after the cabinets are installed, not from the plan. A contractor who orders stone off drawings is gambling — and when it does not fit, the slab is scrap. Confirm the template is taken on site after installation.

The costs that catch people out

These rarely appear on a first quote and regularly appear on the final invoice.

How long it takes

The on-site work is short; the waiting is long. Cabinetry is manufactured to your measurements, and that manufacturing happens before anyone arrives at your house.

StageTypical duration
Design, quoting and final measure1 – 2 weeks
Cabinetry manufacturing3 – 6 weeks
Strip-out and services2 – 4 days
Cabinet installation2 – 4 days
Stone template, cut and fit5 – 10 days after install
Tiling, plumbing connection, paint, snags3 – 5 days

Plan for six to ten weeks from signing to a finished kitchen, of which two to four weeks are disruptive. The stone gap in the middle is unavoidable: the tops cannot be templated until the cabinets are physically in place.

What should be in a kitchen quote

A quote you can actually compare names the materials. If two quotes differ by R50,000, this list will tell you why.

Red flags

Frequently asked questions

How much does a kitchen renovation cost in South Africa?
A facelift — new doors and fronts, new tops, paint, same layout — costs R30,000–R70,000. A full mid-range refit costs R80,000–R180,000. High-end kitchens with stone tops, custom joinery and layout changes run R200,000 and up. Cabinetry and countertop choices drive most of the variation.
What is the cheapest way to renovate a kitchen?
Keep the layout. Leaving the plumbing and electrical untouched removes the two most expensive variables. New doors and drawer fronts on sound carcasses, a new countertop, a new splashback and paint will transform a kitchen for roughly a third of the cost of a full refit.
How much do kitchen cupboards cost per metre?
Melamine runs R3,000–R5,000 per linear metre installed, sprayed Supawood R5,000–R8,000, and solid timber or fully custom joinery R8,000–R15,000. A typical six-metre kitchen therefore falls between R18,000 and R90,000 for cabinetry alone.
How long does a kitchen renovation take?
Two to four weeks on site, but cabinetry manufacturing adds three to six weeks before that starts. Plan for six to ten weeks from signing to a working kitchen.
Which countertop is the best value?
Engineered quartz at R2,500–R4,000 per square metre installed is the best all-round balance — no sealing, very stain-resistant, and it lasts decades. Laminate at R700–R1,400 is the budget choice. Marble looks superb and stains from wine and lemon, so it is a poor family-kitchen top.
Do I need approved plans to renovate a kitchen?
Not for a like-for-like replacement. You do need municipal approval to remove or alter a wall, change external openings, or extend the footprint. Any building older than 60 years needs a heritage permit before alteration — which affects much of the older stock in Stellenbosch, Paarl, Franschhoek and Wellington.
Does a new kitchen add value to a house?
It is the room most likely to influence a sale, but the return depends on matching the spend to the property. A R250,000 kitchen in a R1.2 million house rarely returns its cost. A well-executed R80,000–R120,000 refit in a mid-market home is the range most likely to pay for itself.

Get a kitchen quote you can actually compare

Tell us what you have and what you want, and we will put you in front of renovation contractors who quote line by line — cabinetry, tops, appliances and services separately, so you can see exactly what you are paying for.

Get quotes for my kitchen → WhatsApp us